試題1
While generating the status report for a budget-constrained project,the project manager identifies that the project is one week behind schedule. What should the project manager do t o bring the project back on track?查看答案
試題參考答案:A
試題解析與討論:www.010jia.cn/st/480389300.html
試題2
項目發起人授權項目經理編寫項目章程。項目經理在收集高層次需求時,發現兩位高管意見有分歧,雖然項目經理試圖引導他們達成一致,但效果甚微。項目經理下—步應該怎么做?()查看答案
試題參考答案:B
試題解析與討論:www.010jia.cn/st/498975486.html
試題3
Spike之后找出一個低風險的方案,作為敏捷工程師,你會怎么做?查看答案
試題參考答案:C
試題解析與討論:www.010jia.cn/st/529559900.html
試題4
While reviewing the schedule,the project manager discovers is significant scope creep due to an unforeseen issue. What should the project manager do?查看答案
試題參考答案:C
試題解析與討論:www.010jia.cn/st/479987348.html
試題5
項目經理參與一個指導委員會召開的擴大會議。會議上,一位高級管理人員提出,項目團隊要能保證每位成員在要求的時間完成指定的工作。這屬于以下哪項管理范疇?查看答案
試題參考答案:C
試題解析與討論:www.010jia.cn/st/46840427.html
試題6
Local experts warn that weather condition may impact the project schedule. What should the project manager do next?查看答案
試題參考答案:A
試題解析與討論:www.010jia.cn/st/491123721.html
試題7
一個具體、定義明確的可交付成果正由一家公司位于某個成本較低國家的機構開發。管理層決定將該部分公司出售給另一家組織。項目經理被分配的任務是,替換該機構提供的資源,完成可交付成果。查看答案
試題參考答案:B
試題解析與討論:www.010jia.cn/st/4739814053.html
試題8
A project manager is leading a team developing a new online banking application.After 23 months,the team has spent U SS100,000 on development and has US$70,000 of the budgeted cost remaining. The targeted completion date is 12 months away,but the team expects completion in nine months.A team member identifies a proven off-the-shelf product t hat complies with all project specifications,can be purchased for US$60,000,and can be implemented within eight months. What should the project manager consider?查看答案
試題參考答案:D
試題解析與討論:www.010jia.cn/st/480991666.html
試題9
在定義范圍時,項目團隊識別到一個重大預算限制,并得到項目發起人的確認,若要提早識別到這個問題,項目經理應該事先做什么?查看答案
試題參考答案:D
試題解析與討論:www.010jia.cn/st/469386295.html
試題10
A project manager working on an IT development project dis covers that some codes supplied by a subcontractor fall to conform to project quality standards. The subcontractor refuses to change deliverables without additional payment guarantee s and extended timelines.A client debriefing is due in a few weeks. What should the project manager do?查看答案
試題參考答案:C
試題解析與討論:www.010jia.cn/st/4880928287.html
信管網訂閱號
信管網視頻號
信管網抖音號
溫馨提示:因考試政策、內容不斷變化與調整,信管網網站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!
信管網致力于為廣大信管從業人員、愛好者、大學生提供專業、高質量的課程和服務,解決其考試證書、技能提升和就業的需求。
信管網軟考課程由信管網依托10年專業軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮,通過深研歷年考試出題規律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發表評論 查看完整評論 | |